Basic Site Details

Name: Edinburgh Royal Infirmary, Reproductive Biology Building
City or county: Edinburgh
Country: Scotland
Parish:  
Status:  
Grid ref:
Notes: QS Gibson & Simpson; Main contractor G Percy Trentham Ltd

Building Type Classification

The building is classified under the following categories:
 ClassificationOriginal classification?Notes
Item 1 of 1Hospital block  

Events

The following date-based events are associated with this building:
 FromToEvent typeNotes
Item 1 of 11977 Build/construction 

People

Design and Construction

The following individuals or organisations have carried out design/construction work. Where architects or practices worked together, matching letters appear beside their names in the Partnership Group column.
 NameRolePartnership GroupFromToNotes
Item 1 of 2Robert Matthew, Johnson-Marshall & Partners (RMJM) A1977  
Item 2 of 2Vernon Harry Lee A1977 Partner in charge

Related Buildings, Structures and Designs

Parent Structure and Site

This structure is related to the following parent structure or site (click the item to view details):
 Building nameNotes
Item 1 of 1Edinburgh Royal InfirmaryThe new infirmary at Edinburgh was opened on Wednesday. The late Mr D. Bryce, RSA, was intrusted with the planning of the buildings, of which his nephew and partner, Mr John Bryce, has superintended the completion. The style adopted is the old Scotch Baronial. The Lauriston facade presents a central elevation 100 feet long, with the height of three stories, in addition to a half-sunk basement. From each side of this central building, which is partly appropriated as administrative accommodation, there run out, in the same line, three tiers of corridors giving access to the wards of the Surgical Hospital, and offering, in the front view, as many ranges of large three-light windows surmounted by a stone balustrade. These corridors are continued from end to end of the buildings, and on their north side there are carried out, at right angles, towards Lauriston, four pavilions or blocks of wards, severally measuring 128 feet in length, with an extreme width of 33 feet 2in. In their side elevations the several pavilions show ranges of plain windows, the walls being relieved with string-courses and diversified at the top with stepped gables, small turrets, and chimneys characteristic of the style. The masonry throughout is ashlar, with tooled facings to doors, windows, and gable-heads. There is accommodation for 600 patients. The amount of space provided for each patient varies from 2,350 to 2,380 cubic feet, as compared with 1,800 cubic feet allowed in St Thomas' Hospital, London, and 1,226 cubic feet in Fort Warren, Massachusetts. [Building News 31 October 1879 p536]


CHECK 1890s journal references - are these for work by George Washington Browne?

Structural Engineers Phase 1 Blyth & Blyth; Service Engineers Steensen, Varming & Mulcahy; QS George Berry & Partners; main contractor W & J R Watson

References

Bibliographic References

The following books contain references to this building:
 Author(s)DateTitlePartPublisherNotes
Item 1 of 2Gifford, John, McWilliam, Colin and Walker, David M1984Edinburgh (The Buildings of Scotland) Harmondsworth: Penguin Books Ltdp261
Item 2 of 2RMJM  RMJM Practice Brochure