| June 1960 | | Proposed | £5m 3 single-storey integrated factories (tenders invited shortly); £200,000 site clearance work begun by Robert M Douglas (Contractors) per Builder 17 Jun 1960 p1168 |
| 19 August 1960 | | Contract offered | £500,000 contract for second stage of new factory awarded to Robert M. Douglas Ltd., George Road, Birmingham per Builder p348 |
| 26 August 1960 | | Proposed | approx. 12 English and Scottish contractors invited to submit tenders for £300-400K construction of roadways contract; the closing date is 6 Sept and work is expected to commence in mid-Sept per Builder p399 |
| 30 September 1960 | | Contract offered | £350,000 contract to covert a mile of the A8 to dual carriageway and construct a new subsidiary road with a flyover junction, sliproads and under-passes by April 1961 awarded to John Laing & Son Ltd. per Builder p636 |
| 28 October 1960 | | Contract offered | £2 mil. contract for three factories, including BMC factory at Bathgate, awarded to Melville Dundas and Whitson of Glasgow; work expected to finish in 12 months' time; work under other contracts on the site includes £708,000 by Robert M Douglas Ltd and £350,000 in road works by John Liang and Son Ltd per Builder p810 |