| 1959 | 1960 | Build/construction | Whatling's Ltd. to reconstruct bridge over 14 months at a cost of £151,920 (cost over 18 months would be £147,495) per Builder 24 April 1959 p795 |
| 6 March 1959 | | Scheme accepted | 'Perth Town Council ...given a 75 per cent grant from the Secretary of State for Scotland towards the cost of replacing the Victoria Bridge...estimated cost of £145,000, of reinforced and prestressed concrete, consisting of a central arch span of 187 ft. 5 in., and two cantilevered end spans of 112 ft. and 78 ft. 5 in. The immediate approaches to the bridge will also be improved...including a revised layout of the junction with Gowrie-street and Dundee-road.' per Builder p477 |
| April 1959(?) | October 1960(?) | Build/construction | estimated start in April 1959; estimated completion between Oct 1960 and April 1961 |