| 14 June 1957 | | Plans prepared, construction not yet begun | 'plans prepared by the City Architect...est. cost ₤500,000'; 29 acre site; accomodation for 1,400; hope to start building 1958 - per Builder p1102 |
| January 1959 | August 1959 | Plans prepared, construction not yet begun | 'building contract awarded to Truscon Limited. Charles Gray Limited, of Dundee, will be sub-contractors for the general building trades. Work...to start in January 1959, and completion, in two stages, is planned for February and August 1960.' per Builder 23 Jan 1959 p209 |
| March 1959(?) | | Build/construction | 'Work has commenced...the school will accomodate 1,700 pupils and cost nearly £500,000.' per Builder 3 April 1959 p664 |