The following date-based events are associated with this building:
From
To
Event type
Notes
1809
1811
Original school
22 June 1844
Offices for schoolmaster's house - plans and specifications approved
13 July 1844
Offices for schoolmaster's house - tender accepted
18 August 1845
Offices for schoolmaster's house - completed
9 April 1861
Plan and specifications commissioned for addition
21 May 1868
Schoolmaster's house completed
8 August 1868
Plans and tenders accepted for new schoolmaster's house
1879
Additions and alterations
1880
Additions and alterations
1890
Additions and alterations
1902
Alterations and additions and plans of offices
1914
Workshop, alterations and additions
People
Design and Construction
The following individuals or organisations have carried out design/construction work. Where architects or practices worked together, matching letters appear beside their names in the Partnership Group column.